January 4, 2021 - We’ve never been so glad to see a roof project begin…
January 5 - Ripping off the old underlayment and applying new and thicker wood decking…
January 11 - Goodbye, concrete tiles! St. Joseph, pray for us!
January 13 - All the tiles are off the retreat house, and the new ice and water shield underlayment is starting to be applied.
January 14 - Flashing in the valleys…
January 14 - Hurray for our Helming Brothers roofing crew!
January 14 - Soon, this whole roof will be red clay tile!
January 21 - Concrete tiles starting to come off the chapel…
March 4 - The new clay tiles are lined up and ready for installation!
March 4 - an elevator to get the tiles on that roof!
March 4 - So many tiny piles of clay…
March 4 - Smile — we’re finally installing the new roof!
March 4 - almost finished removing tiles on the chapel clear-story in preparation for custom tile measurements.
March 5 - The chapel roof is tucked in and waterproofed to await its turn for new tiles.
March 5 - It’s starting to look like a roof again!!!!
March 5 - Ludowici Spanish 18” clay tiles: blended, stacked, and ready to go!
March 5 - A closeup of the Spanish tiles on the retreat house.
March 6 - make sure those lines are straight and those headlaps are even!
March 6 - if YOU had a giant crane at your disposal, wouldn’t YOU ride it up as high as you could, too?
March 24 - retreat house roof is almost complete, and the red fascia is installed
March 24 - the nuns are helping by blending the tiles onto pallets, so the roofers can stay on the roof!
March 30 - progress from the lift view: the valleys on the retreat house are slowly getting filled in!
March 30 - each tile along the valley needs to be measured and cut to fit
March 30 - a beautiful new roof, with piles of roof tiles in the background, waiting to be blended by nuns and volunteers
March 30 - See the difference: new clay tiles in foreground, old concrete tiles in background!
March 30 - Helming’s crew hard at work…
March 30 - Shape up! The Mother Superior is making a site visit!
April 13 - The retreat house roof is finished!
April 13 - more tiles being removed and new decking applied to our chapel
April 22 - work on the chapel roof is progressing
April 27 - this week’s project is the highest peak
April 27 - roofers already up and at it at sunrise!
May 3 - Where is the water coming in????? [we did find our answer eventually]
May 6 - working on chapel roof section #6
May 13 - only two sections of old tile left on the chapel!
May 15 - completing the demolition of our chapel roof!
May 26 - loading tiles onto the last chapel roof section!
June 4 - only the details on chapel remain to be done. Doesn't it look great?
June 9 - work has begun on our work wing roof
June 17 - the crew has entered the cloister courtyard as they round the corner on our work wing
June 18 - new 3/4 inch plywood decking going up...
June 22 - the door to the dump truck was left ajar after hours, and the nuns couldn't help themselves; they had to install a driver to greet the crew in the morning!
mid July - the work wing nears completion
mid July - the crew has rounded the corner and passed the bell tower!
mid July - the final sections of the roof are in sight!
July 22 - demolition of the final roof section, our dormitory wing, has begun!
July 22 - underlayment applied and awaiting the tiles!
July 22 - look at that chapel roof!
August 5 - Mother John Mary and Sr Frances Marie get in on the action on the front roof of the monastery
August 5 - Sr Mary Veronica perches on the bell tower!
August 5 - the view is great from the belltower!
August 5 - it’s really starting to look like a clay tile roof
August 5 - Helming’s crew hard at work
August 15 - the last shipment of roof tiles has arrived!
an August Friday - late nite tile blending
August 18 - hoisting a new gutter to the roof of the cell wing
September 1 - Marathon Tile Day: beginning to lift tiles onto the final two sections of roof
September 1 - Marathon Tile Day: Our heroic crew lifted and distributed 80,000 lbs of clay tile onto the roof in one day, to save us money on the telescoping forklift rental!
September 7 - a few days later, all those tiles are being laid and fastened… the end is in sight!
late September - racing to secure the bell tower flashing against a Kentucky thunderstorm
early October - almost done!
October 11 - beginning the overhaul of our Retreat House stairwell roof
March 10, 2022 - Completed at last!!
March 10 - A view of the completed eastern-side roofs
March 10 - The completed work wing roof, with Retreat House and chapel visible in background
March 10 - Doesn't that new roof look lovely next to the shining blue lake?
March 10 - A panorama view of the entire completed roof, seen from the cloister side
March 10 - Joe Helming gifted us with a beautiful high-polish stainless steel cross for our bell tower!
March 10 - The new small cross is a scale model of the large chapel cross
March 10 - a blessing ceremony for the new cross
March 10 - Father Lou, Oblate Mike, and Joe Helming, ready to start the blessing!
March 10 - A confirmation from Heaven ... as soon as the cross was blessed, the sun came out from behind a cloud!
March 10 - THANK YOU to all of our benefactors, friends, and hardworking Helmings crew -- we could not have done it without you!!